A) KITCHEN WORK
1Supply labour and tools to hack off Kitchen entrance wall (includes submission & application to HDB for approval)
2Supply labour and tools to make good damage walls area after hacking
3Supply labour and materials to construct cabinet base (50mm) complete with side tiles
4Supply labour and materials to construct washing machine base (50mm) complete with full tiles (OPT)
5Supply labour and materials to construct fridge base(50mm) complete with full tiles
6Design, fabricate and install (30FT) top and botton kitchen cabinet using laminted materials, inclusive of:
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Shelving,
- Soft closing hinges (BLUM)
- 1 nos stainless steel dish drainer with BLUM hydraulic glass cover,
- 1 nos Cutlery tray
- 10 nos drawers with BLUM tracks,
- internal adjustable carcass shelving
7Supply labour and materials to install QUARTZ / KOMPACPLUS kitchen worktop with 50 mm backsplash
8Supply labour and tools to instal basin with tap and cooker hob and hood
9Supply labour and materials to instal 1 full height tempered glass (10mm)sliding door c/w frame
- Includes inter-locking device at hacked wall opening area
10Design, fabricate and install L-shape Island counter (14FT) using laminted materials, inclusive of:
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
- 3 nos drawers with BLUM tracks,
- internal adjustable carcass shelving
11Supply labour and materials to install QUARTZ / KOMPACPLUS for island counter
12Design, fabricate and install (4FT) tall unit vertical pull out larder using Laminated materials, inclusive of
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
- 3 nos drawers with BLUM tracks,
- internal compartment selected color PVC finishes
- internal adjustable carcass shelving
- at the opposite side inside kitchen with Slim storage compartments
13Supply labour to install 1 set of kitchen cooker hob and hood
14Supply labour to install oven and microwave oven
PLUMBING WORKS
1Provision of water points & provide labour to install WC sprayers at 2 toilets
2Supply / install in/out-let pipes for kitchen sink & island sink (total 2 sinks)
3Supply/ install in/out-let pipes for basin at 2 toilets
4Supply/ install in/out-let pipes for washing machine
5Provide labour to install 2 x instant heater or centre heater at common toilet (including piping & Electrical connection)
6Provide labour to install kitchen sinks and taps (2 sinks)
7Provide labour to install all bathroom & toilet accessories
8Supply labour to dismantle and install existing basin for both bathroom (if needed)
9Supply labour to install tap for new basin at both bathroom (if needed)
B) LIVING ROOM
1Supply labour and material to alter existing DB box with laminate and install 5 pc of shelving
2Design, fabricate and install (6FT) full height shoe cabinet with solid Plywood using laminated materials, inclusive of:
- Internal Compartment selected Colour PVC Finishing,
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
3Design, fabricate and install (10FT) full height TV feature wall with suspended TV Consol with drawers using laminated materials, inclusive of:
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
- Black tinted glass panel
4Supply labour and material to install (10FT x 4 FT) tinted mirror at dining area
C) BEDROOM 2 WORKS
1Supply labour and tools to hack wall between bedroom 2 and master bedrrom
2Supply labour and tools to make good damgaged walls area after hacking
3Supply labour and materials to construct (4 inch) height platform bed curve design completed with EVORICH HERF finish, inclusive of:
- half height bedhead rest (10 FT)
4Supply labour and materials to construct storage bench by the window, inclusive of:
- Internal Compartment selected Colour PVC Finishing,
- Soft closing hinges
5Supply labour and materials to install Tempered glass (10mm) sliding door (2 panels ) at bedroom divide
6Design, fabricate laminated TV console at the fixed wall panel
D) MASTER BEDROOM
1Design, fabricate and install (10 FT) with laminated finish L shape suspended study table with drawers at master bedroom, inclusive of:
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
2Design, fabricate and install (4.5 FT) with laminated finish top hung casement cabinet, inclusive of:
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
3Design, fabricate and install (4.5 FT) with laminated finish cabinet along the wall, inclusive of:
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
4Design, fabricated and install (16 FT) full height walk-in L-shape wardrobe, inclusive of:
- with hidden sliding door design
- make good and cover up with partition wall to the back of the wardrobe along the bedroom
- Internal Compartment selected Colour PVC Finishing,
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- tempered glass sliding door (OPTIONAL - add on fee at $$$?)
- drawers c/w locks
- clothes hanging rods
*** To follow illustration designs to fabricate***
5Design, fabricate (4 FT length x 2 FT wide x 3.5 FT height) acessories cabinet with clear glass and accessories compartment drawer, inclusive of:
- Internal Compartment selected Colour PVC Finishing,
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
- 3 nos drawers with BLUM tracks,
- drawers c/w locks
6Design, fabricate (5 FT) length laminated finish suspended dressing table, inclusive of:
- Internal Compartment selected Colour PVC Finishing,
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
- 2 nos drawers with BLUM tracks,
- drawers c/w locks
7Design, fabricate (2.5 FT) shelving with laminated finish inclusive of:
- Internal Compartment selected Colour PVC Finishing,
E)MASTER BATHROOM WORKS
1Supply labour and tools to construct 50 mm (height) shower kerb with full tiles finish
2Supply labour and materials to install (2 FT x 6 FT) 10mm tempered glass fix panel shower screen
3Design, fabricate full length mirror, laminated finish casement cabinet with sloft closing hinges (BLUM)
4Design, fabricate (2.5 FT) length laminted finish vanity cabinet inclusive of:
- Internal Compartment selected Colour PVC Finishing,
- 2-tone laminate,
- 45* trimming,
- ABS Trimming ,
- Soft closing hinges (BLUM)
5Supply labour and material to install (2.5 FT) length casastone QUARTz as vanity top
FCOMMON BATHROOM WORKS
1Supply labour and tools to construct 50 mm (height) shower kerb with full tiles finish
2Supply labour and materials to install (2 FT x 6 FT) 10mm tempered glass fix panel shower screen
G) CEILING WORK
1Supply labours and materials to construct plaster-fibre false ceilng with cove light design at:
- Living room / dining area
- corridor walkway
- master bedroom
- bedroom 2
- laminated wood material for ceiling finish in the living room / dining area
H) MISC
1Supply and install window grill for whole unit
2Supply and install designed partition wall at existing master bedroom entrance
3HDB Renovation perimt application and processing
4Supply labour and materials to provide chemical washing upon completion
5Supply labour and materials to lay corrugated paper to protect existing tiles during works
6Supply labour and materials to paint whole house using NIPPON All-in-One paint (up to 5 colours plus ceiling white)
7Supply labour for haulage and debris disposal of all waste under renovation
8Supply labour too install light fixtures to original light points